Tampa Executive Airport (KVDF) is experiencing a growth spurt, adding four hangar facilities that are all scheduled to be available by late 2026.
The hangar projects by various private developers mark one of the largest general aviation infrastructure expansions to date for Hillsborough County Aviation Authority facilities at KVDF, according to airport officials. The four hangars will add about 42,000 total square feet of space to KVDF and are the result of more than $6.4 million in private investment.
The first hangar completed was a nearly 12,000-square-foot project started last summer by KVDF FBO Skyport and was finished in March 2026. An additional 20 vehicle parking spaces were included in the scope of the construction.
The second hangar project that started in June 2025 will add another approximately 12,000 square feet of hangar space and is more than 50% completed. It is anticipated to be completed by end of summer.
The third hangar project will be an approximately 12,000-square-foot hangar split into two hangars that are about 6,000 square feet apiece. This project is in early construction phase and should be completed by year end.
The fourth hangar will be approximately 6,000 square feet and is currently in final permitting. The project should also be completed by the end of 2026, airport officials reported.
“The new hangars will add significant capacity and strengthen economic activity to position KVDF for long-term growth,” airport officials added.
For more information: TampaAirport.com